Sample assessment

What an assessment looks like.

This executive decision brief is illustrative. The project, figures and client are fictional, and are used only to show structure and depth.

Cherrug ReviewPage 1 of 4

Executive Decision Brief

Kestrel Ridge Gold Project (illustrative)

Prepared for:
Family office considering a US$12m equity investment
Scope:
Level 2 — Standard Assessment

1. Decision question

Should we commit US$12m for a 15% equity interest to fund the Kestrel Ridge feasibility study and early works?

That's the question we answer.

2. Evidence register

ER-01NI 43-101 technical report (2025)
ER-02Preliminary economic assessment & financial model
ER-03Draft shareholder agreement
ER-04Use-of-funds schedule
ER-05Mining licence & environmental permit correspondence
ER-06Management presentation (March 2026)
Material material concern or inconsistencyClarify incomplete, unsupported or needs clarification
Confidential · Illustrative sampleFictional project · for illustration only
Cherrug ReviewPage 2 of 4

3. Source extracts, annotated

Technical report · Table 14.3 / §22ER-01

Long-term gold price used for reserves and economics:

US$2,100/oz

Mine plan, years 1–5: 62% of ounces Inferred

Follow the number →
Financial model · Inputs!C4:C9ER-02
Gold price (flat)2,400
Recovery93%
Access road capex—
≈30% lower at report price
Permit correspondence · letter 3ER-05

"…construction of the access road shall remain the responsibility of the developer. Community consultation remains outstanding…"

Does the model include this? No.
Use-of-funds scheduleER-04

Total proceeds

US$12.0m

Feasibility study and early works

Gap to decision point: est. US$4–6m

93% recovery — where is the metallurgical test work for transitional ore?

Each extract is reconciled against the others. Where two sources disagree, the difference is recorded as a finding with its evidence reference.

Confidential · Illustrative sampleFictional project · for illustration only
Cherrug ReviewPage 3 of 4

4. Principal findings & unsupported assumptions

  1. F1ClarifyER-01

    The resource estimate is credible, but 62% of ounces in the first five years of the mine plan are Inferred, not Indicated.

    Decision implication: Early-year cash flows rest on the lowest-confidence resource category. → Action 3

  2. F2MaterialER-01ER-02

    The financial model uses a gold price of US$2,400/oz flat; the technical report uses US$2,100/oz. Value at the report price is approximately 30% lower.

    Decision implication: The headline valuation is not supported by the project's own technical report. → Action 2

  3. F3MaterialER-02ER-05

    Capital cost excludes the access road referenced as the developer's responsibility in permit correspondence.

    Decision implication: Capital cost, and therefore the funding requirement, is understated. → Action 4

  4. F4MaterialER-03ER-04ER-06

    Proceeds of US$12m fund the feasibility study but leave an estimated US$4–6m gap to the stated decision point.

    Decision implication: The investment does not reach the stated decision point on its own. → Action 3

  5. F5ClarifyER-02

    Processing recovery of 93% is stated without supporting metallurgical test work for the transitional ore.

    Decision implication: Recovery drives revenue; the assumption is not yet demonstrated. → Action 1

  6. F6ClarifyER-05

    Permit timing assumes approval within six months; correspondence indicates an outstanding community consultation.

    Decision implication: Schedule and funding runway may both be optimistic. → Action 4

Confidential · Illustrative sampleFictional project · for illustration only
Cherrug ReviewPage 4 of 4

5. Risks and opportunities

  • Risk: Dilution if the funding gap is closed by a later raise on less favourable terms.
  • Risk: Schedule delay from outstanding consultation and road responsibility.
  • Opportunity: Oxide cap could support a smaller, earlier heap-leach start, not yet evaluated.

6. Financing implications

At the current stage the project is unlikely to attract senior debt. A future financier will require Indicated-category support for early production and an independent capital estimate including infrastructure.

7. Recommended next actions

  1. Request the metallurgical test work underlying the recovery assumption. (from F5)
  2. Ask management to reconcile model and report gold price assumptions. (from F2)
  3. Make investment conditional on a funded plan to the decision point. (from F1, F4)
  4. Seek clarity on access road responsibility and cost before signing. (from F3, F6)
Resolve these before signing — not after.
Confidential · Illustrative sampleFictional project · for illustration only